Startup
operation
1. Press the start
button to start the standby generator. At the same time, pay attention to the presence
of mechanical noise, abnormal vibration and so on.
2. During operation, the
operator closely monitors the voltage, frequency, current, power factor, oil
temperature, oil pressure, water temperature, charging current, speed and other
instrument instructions and changes of generator set through the instrument.
When the specified value is exceeded, timely inspection and measures should be
taken, and the operation can be continued only after returning to normal.
3. The emergency stop
button on the control screen panel is only used in case of emergency. After
pressing the button, the generator will stop immediately and sound-light alarm
will be issued at the same time.
4. After the generator
runs normally, close the main switch (low-voltage air switch) of the generator
set, and the generator supplies power to the electrical load.
Shut
down
1. After the mains power
is normal, gradually cut off the load and disconnect the main switch
(low-voltage air switch) of the generating set.
2. In the state of
no-load, gradually reduce the speed to idle speed, and wait for the diesel
engine water and oil temperature to drop below 70°C before stopping.
3. Disconnect the
start-up control power, and close the isolation switch to the mains power
position in the order of operation.
Manual
operation
Check before starting:
1. Turn on the power
2. Check if the
following items are normal:
(1) Water tank level
(2) Oil and diesel oil
level
(3) Battery voltage
(4) Battery water level
3. Check the control
panel, switch the main switch to the stop position, close the detection switch.
After the display is normal, turn on the detection switch, each instrument
should display zero, and the indicator light shows shutdown.
Starting
up
1. Switch the main
switch to the manual start position, the generator should start immediately,
and the indicator light shows normal.
2. Observe the various
instruments on the control panel, which should work normally.
3. To operate with load,
close the power output switch.
Shut
down
1. First cut off the
back-end load and then turn off the power output switch.
2. After no-load
operation for five minutes, turn the main switch to the stop position.
3. After checking that
everything is normal, turn the main switch to the automatic start position and
close the power output switch.
Automatic
operation
(I) Please refer to the
manual operation for inspection before starting, but cut the generator to the
automatic starting state after inspection and close the power output switch.
(2) Power on: Cut off
the mains power and observe if it starts automatically.
(3) Shutdown: Turn on
the mains power and observe whether the power is switched automatically and
shut down automatically.
Emergency
shutdown
(1) In case of
emergency, when the protection device of generator itself refuses to start, the
generator should be shut down urgently and the main switch should be switched
to the off position.
(2) After the emergency
shutdown, carry out a comprehensive inspection of the generator immediately and
resume normal operation as soon as possible.
Remarks:
1. No-load operation of the
generator shall not exceed 15 minutes.
2. After the generator
is started, check the water level, oil level, diesel level, battery voltage,
and battery fluid of the generator to maintain normal condition.
3. Make a running record
for each test or automatic start operation.
Comments
Post a Comment