We can install generator
damp proof heater and control panel moisture-proof heater on emergency diesel generator to resolve moisture problem. Because generator damp proof heater and
and control panel moisture-proof heater is optional part, when users purchase,
should tell the supplier.
The
attention on moisture-proof for diesel generator set:
1.Heating and drying shall
be carried out in clean air, and the generator shall be blown clean with
compressed air before drying. If the winding is seriously wet, it needs to be
dried by hot air method first. After drying, dry with load to avoid insulation
breakdown. When drying, we should put more thermometers in the parts of
industrial diesel genset, so as to grasp the temperature of each part and
reduce local overheating. Heating shall be carried out slowly to avoid
insulation damage caused by sudden evaporation of moisture in the coil.
2.If the drying
temperature does not reach the required temperature, it can be dried at a
slightly lower temperature. But the time should be lengthened properly. Measure
temperature and insulation resistance every 30min after drying. when the
temperature is stable, measure every 1-2h and make records.
3.In the early drying
stage of diesel generator set, due to the heating of winding and the
evaporation of water, the insulation resistance will decrease. And then
gradually rise, the speed of rise is more and more slow, final stable at a
certain value.
When the insulation
resistance is kept constant for more than 3 hours at a constant temperature,
the drying can be finished. Either way, after drying, when the coil is cooled
to 60℃, the insulation
resistance of stator winding and hand winding shall be measured with 500V
megger and shall not be less than 0.5MΩ.
In order to let the unit
work normally, there should not have water, oil, sewage, corrosive gas etc.
around the unit to avoid damaging the insulation of generator set. The
temperature of cold air shall not be too low to avoid condensation on the winding
and other conductive parts.
When making dampproof,
pay attention not to affect the normal ventilation and cooling of the generator
set. Always clean the dust and dirt in the ventilation duct and keep it
unobstructed. For the generator that stops running for a short time for some reason,
the collector ring does not need to be protected by holding brake, however,
insulating cardboard, paraffin paper or asphalt paper shall be padded between
the brush and the collecting ring to avoid spots on the surface of collecting
ring caused by electric brush. In terms of the processing of the generator, if
the paint is rusted due to falling off, the rust shall be removed in time and
the antirust paint shall be applied.
Here
are some other ways to dry diesel generator set:
1.Cold
operation method.
When the AVR power line
is disconnected, the generator set placed in dusty or humid environment for a
long time can be idle for about 10 minutes. This may be enough to dry the
winding surface and increase the insulation resistance to more than 1 MΩ to generate
electricity.
2.Hot
air method.
Remove all covers of the
generator set in order to remove the moist air. Use a blower to blow in from
the air inlet of the generator set. Please note that the heat source and
winding should be kept at least 300 mm to avoid overheating and insulation
damage, and control Surface temperature of winding. The winding surface
temperature shall not exceed 85 ℃
and the inlet temperature shall not exceed 90 ℃. Continue blowing every half hour and record
the insulation resistance value. When the value is greater than the specified
value, the drying process is completed. Remove the blower, close all covers,
and try again.
3.Drying
method of short circuit current.
Firstly, carry out the
safe operation of the mechanical and electrical equipment of the unit to ensure
the safe operation of the generating set. The output end of the generator set
is short circuited through the short circuit piece, which shall be able to bear
the rated current of the generator set. Disconnect AVR(Automatic voltage
regulator) and switch to external 0 ~ 24V DC power supply, adjust DC power
supply voltage to make each phase current of stator 50-70% of rated current.
Stop every 30 minutes, disconnect the external excitation power supply, check
and record the insulation resistance value. If the insulation resistance is
greater than the specified value, the external DC power supply can be removed,
and AVR can be reconnected and re-debugged. The generator set can operate at
rated speed, but the speed shall be kept constant to avoid temperature
instability.
4.Drying
method with load.
If only the surface is
wet, we can dry the unit with load. When drying, The generator set can operate
at 50% of rated current load. Then increase the rated current by 65%, 85% and
100%. The load for each phase is 4 to 5 hours. During the drying process, the
insulation resistance of each winding shall be tested regularly. After the
insulation resistance meets the requirements, the drying can be stopped and the
generator set is usually tested.