The emergency generator
shall retain sufficient (not less than 600 mm) space around the generator for
maintenance and cleaning. The ventilation system shall be adequate to meet the
requirements of the combustion process and cooling of the air. If it is
necessary to use a fan to supply the air, the fan should be operated at the same
time when the generator is on. The air shall be directly inputted or discharged
without any obstruction, that is, fire dampers, smoke gates, or adjustable air
gates shall not be fitted.
If the piping for the input and / or discharge of
air is not entirely built in the room in which the generator is placed, but
passes through an adjoining room or unit, the fire resistance of the pipe shall
be equal to that of the fire resistance of the room in which the generator is
placed or of the fire resistance of the room through which the generator is
placed, Whichever is the greater. Emissions from combustion shall not cause
nuisance to the public and shall be discharged in accordance with the
guidelines and requirements of the Environmental Protection Department.
Operation
of Emergency Diesel Generator Set
1. Operating Procedure
① When the
mains power fails, the generator should be started in time.
② Check that
the oil, diesel, battery, and voltage are normal before starting. Is the water
level in the water tank sufficient?
③ Check if the
blades and drive belts are normal, check for oil leaks and other loose
connections throughout the fuselage.
④ The starting
time should not exceed 5 seconds. The two consecutive starts are unsuccessful.
The interval should be 2 minutes after the Nankang generator is rented out. If
it cannot be started after three times, the cause should be found.
⑤ After the generator
is powered normally, it should be observed that the operation of each
instrument is normal. If abnormal conditions are found, stop the inspection
immediately.
⑥ Keep the
unit load not exceeding 80% of the customer's value during operation.
⑦ After the
mains supply resumes power supply, the mains is converted by reverse operation
according to the startup procedure. Keep running at no load for more than 5
minutes before stopping.
⑧ During
operation, pay attention to turning on the blower.
⑨ After the
emergency generator is started, it should be separated by 2 hours, and the
voltage, current, oil pressure and water temperature should be recorded.
⑩ In
operation, to ensure the normal and safe operation of the generator set, the
unit must be inspected by a combination of watching, listening, smelling and
touching.
2.
Daily inspection and maintenance of emergency generators
① Check the
fuel level of the fuel tank and the water in the water tank. If it is
insufficient, it should be added.
② Check the
oil level and add enough if not enough.
③ Check the
stability of each accessory installation, the anchor of the anchor and the
mechanical connection.
④ Check the
machine for oil leaks and water leaks.
⑤ Check
whether the meters are normal, whether the battery battery water is sufficient,
and check whether the battery voltage is normal.
⑥ Clean the
appearance of the machine and accessories.
⑦ The
generator is placed in an automatic standby state and the battery is placed in
a charging state.